Thursday, April 24, 2008

Ooo... Pretty Pictures

Here are the pictures of the roof that I promised! First, here is one of my copper roof jacks. The squirrels around here EAT the lead roof jacks right off the roof! So copper is the way to go. It's more expensive, but it's cheaper than having to replace them every 2 years or so once the squirrels have had their fill:



The next photos show different views of the completed roof:








Finally, here's a shot of the back door of the house now that it's installed. I'm in the process of priming and painting this and the entry door to the rear garage before the brick layers begin their work. That could happen as early as this Saturday!



Saturday, April 19, 2008

Roof & Exterior Doors Installed

With the plumber's installation of the roof jacks completed, I was ready for the roof to go on. I had narrowed it down to three roofers. Each bid coming in at just around $8,000 and each bidder having nothing about them to make them stand out from the rest. I went with a guy who lives across the street from a relative. he had helped my relative put a roof on a shed and seemed interested in getting it done the right way.

They worked on Thursday and Friday of this week (4/17-4/18). The roof looks good! (Pictures to come on that.) I was there most of the day on Thursday. That's when all my exterior doors were delivered. The only question I have about the roof is the ridge vent in the rear garage. It seems higher at each end than in the middle, like it's bowed or something. I need to ask him about that before I pay him.

As for the doors, here are pictures of them before installation:






I knew they were coming on Thursday so I called the framer on Wednesday to let him know. I expected that I'd have the weekend to start painting and staining the doors before he installed them. I still needed to pick out the stain for the front door and the primer & paint for the back doors.

My mom and I got up early today (Saturday) to pick up a piece of the front door moulding from the house and bring it with us to the paint store. The framer had never worked on Saturday at my job before, but alas, he was there this morning installing the doors! That's a good thing, don't get me wrong. But it meant that I couldn't paint all the doors and door frames before they went up. While it's not the end of the world or anything, I can't water seal the bottoms of the door frames to prevent rot like I would have preferred.
Since the doors have been delivered and installed about 3 weeks sooner than I had planned, I now need to cirlce back with the brickyard and the brick layers to see if they can fit me in earlier than expected.

Monday, April 7, 2008

Rough-ins Coming to a Close; Hunting for Materials

Last week, my air conditioning guys finished their work (and he's ready for his first payment). The electrician finished running all his wire on Friday, and my plumber started working on his pipes and vent stacks on Saturday. I've been stressing out over ordering materials that I should have had already, like the exterior doors, the heater/vent/lights for the bathrooms, and some stuff that the plumber needs in order to finish his work. I've got my two bids on this stuff. Now it's a matter of comparing the prices and the different brands offered.

Like everything else, the heater/vent/lights are not a straighforward thing to get. There are choices among brands, among noise levels, among how many cubic feet per minute (CFMs) they can vent, and even among features. Some have a night light. Most don't have a heater. Some just have a fan. Uggh! Make it stop! :)

It also turns out that I'm going to be running all my own telephone, cable, and computer wires everywhere. I originally thought I would be doing that, and then my electrician told me he had assumed he was doing it. That was a relief in a way. I looked forward to doing it so I could say I did something like that on my own house, but then again I know it's a lot of work. He took longer than he planned with the electrical wiring, so he made a deal with me to reduce his fee and let me run the other stuff. So I'm saving money and getting the chance to do something I want to learn about. On the flip side, it's going to take me some time since I'm new at it.

I've decided on my bricklayers. I'm going with the very first ones I talked to. They are cheapest (at $8,020), and their work was very good. The woman I'm working with at the brickyard also highly recommends them. I just called him tonight and setup a meeting tomorrow so he can look at the house.

The brickyard sent me home with a few samples of my Magnolia Blend bricks, along with samples of different kinds of pavers to go on the front porch and back patio. The samples of my brick are all pretty much the same color, so it's not easy to pick out the roof color and the pavers.

As for roofers, I'm waiting on one final bid. The neighbor behind me used them to replace her roof after Katrina. They came out to measure on Friday (and the guy left his ladder), but he hasn't given me a price yet. The owner sent one of his supervisor-type guys to measure, and I asked him to look at where the roof is leaking through the felt. He said he had a guy who could stop by that evening on his way home and fix the felt so it wouldn't leak. Of course, that guy never came. It rained that night, and I found some new spots where it leaked. According to the bids I have so far, I'm going to need somewhere between 55 and 68 squares. A square is a 10ft x 10ft area.

On my latest bill from the lumber yard, they haven't credited me for 3 rolls of Tyvek housewrap I sent back. So I've been on the phone with them to take care of that. I think that's all the brain dump I'm capable of right now. More later...

Saturday, March 29, 2008

Electrical Rough-in

My electrician and his helper worked half a day on Friday and all day today. They were able to wire most of the electrical stuff in the house. That leaves the structured wiring (telephone, cable, and data) in the house (and the power to the garage) for them to finish up this coming Friday or so. I have some homework to do in deciding what I want run to which box. Some will get just a telephone and data jack. Others will get multiple data lines, or a coax cable hookup, etc.

I finally got the plumber on the phone today. He wants to meet me at the house tomorrow to give me a list of stuff I need to buy in the next few days as he starts his rough-in.

My parents and I cleaned up the yard of all the scrap lumber and some lumber I need to send back. We also broke up some excess concrete that had been puddled in the front yard on the day of the slab pour.

I noticed today that the framers installed a window in the wrong place. There are two identical windows in a row next to the back door. One has tempered glass, and it needs to be the one right next to the door. They put the other one next to the door, so they'll need to swap them out.

We also built up the level of my kitchen island bar to 44 inches. The framer had built it to about 41 inches. This didn't leave enough space to comfortably fit the outlets in the backsplash. We added a couple of layers of 2x4s to the top to make up the 3 inches.

It rained for a while this afternoon, and my friend spotted a leak in the felted roof over the fridge in the kitchen. I'm glad I found that early and can let my roofer (whoever that will be) know about it. I've gotten two bids in for roofing so far. Another has measured and I'm expecting a bid from him. And I also want to try the people who did my rear neighbor's roof. They did a good job.

I really gotta post some more pictures...

Sunday, March 23, 2008

Felt on the Roof

The framers finished the plywood and felt on the roof of the house this Friday (3/21). They also put the housewrap on the house. Now it's ready for the other subs to come do their rough-ins. My AC guy will call Monday morning to let me know what day he can start. It looks like the plumber will come in after him. And my electrician is hoping to get in there this Friday and Saturday. We'll see if that all pans out...

They still need to put the roof and the wrap on the Garage. The windows will be delivered this Tuesday, because that's when the framer said he'd be ready for them. I paid the framer his first $10,000 on Friday.

I went to Lowe's this week to buy all the wiring my electrician told me to get. Total cost: $1,800!

I've been looking again at front entry doors. I can get one for around $1,800 - 2,000, but it doesn't have the window configuration I like. It is however, narrow enough. I can't have two 36" doors. I need more like 32". The ones with my preferred windows are too wide (and too expensive at $46,00)!

I've got 2 insulation bids. Both around $9,000. I have one roofing bid so far, with another one scheduled to come out and measure this week.