My gutters are installed now with the downspouts not extending to the ground. This is so the driveway guys can place drains and work without banging up the downspouts. They look good! Pictures to come soon.
My mechanical inspection failed today because they didn't setup a fresh air intake. Because I've sealed the attic with foam, they claim I need to mix fresh air into the circulation system from outside... The new A/C guy (who replaced my original one when he moved out of state) said they should have known that but overlooked it somehow. I thought I had asked the original guy if I needed it. Maybe I didn't. Anyway, he says it "probably" won't cost me anything to add. So that's good.
I paid my deposit for the pavers today and signed the contract. Delivery should be in about 2 weeks, and the process may take about a week once they get started. I need to buy the materials for the drainage and also check to see if the parish is going to have to approve my drainage plan.